References Civil Engineering
[Translate to English:] Neubau Wandersmanntunnel ICE-Strecke Köln - Wiesbaden
| 2000 | Implementation planning and static calculation open building pit lining Implementation planning and static calculation tunnel segments |
|---|---|
| Constructor: | Deutsche Bahn AG |
| Planning: | Arge NBS Köln-Rhein/Main, Dyckerhoff & Widmann |
| Construction Time: | 01/1998-04/2002 - Opening May 2002 |
| Planning Phases: | Work phase 3 – 5 |
| Static calculation of construction pit reinforcement, dimensioning of drilled piles and tunnel segments Design of the supporting structure planning execution drawings (positions of joists for construction pit reinforcement, connection details etc., drawing up formwork plans and structural drawings for drilled piles and tunnel segments) |